|
Electricity
The Hongkong Electric Company Limited (HEC) supplies
Hong Kong Island and the neighbouring islands of Ap Lei Chau and Lamma;
CLP Power Hong Kong Limited (CLP Power) supplies Kowloon and the New Territories,
including Lantau and several outlying islands. The supply to consumers
is at 50Hz alternating current while the voltage is 220 volts single-phase
and 380 volts three-phase.
   The
two supply companies are investor-owned. The Government monitors
their performance through mutually agreed Scheme of Control Agreements.
Current agreements with CLP Power and HEC came into effect on October
1, 1993 and January 1, 1994, respectively. Both will last for 15 years.
The first five-yearly interim review was completed in early
1999. The next review will be carried out in 2003. The agreements require
each company to seek the approval of the Government for certain aspects
of their financial plans, including projected tariff levels. The agreements
do not grant the companies any exclusive rights. They are not franchises,
nor do they define a supply area for either company or exclude new entrants
to the market.
   Electricity
for HEC's supply areas is supplied from the Lamma Power Station. At the
end of 2001, total installed capacity (i.e. rated power output of generators)
at the Lamma Power Station was 3 305 megawatts (MW). In May
2000, the Government approved HEC's new power station at the Lamma Extension
and the installation of the first 300MW gas combined-cycle
generator there. The unit is scheduled to be commissioned in 2004. HEC's
transmission system operates at 275 kilovolts (kV), 132kV and 66kV and
distribution is effected mainly at 11kV and 380 volts.
   The
Castle Peak Power Company Limited (CAPCO), which is 60 per cent owned
by ExxonMobil Energy Limited (formerly known as Exxon Energy Limited)
and 40 per cent by CLP Power, supplies electricity to CLP Power from its
Black Point (1 875MW), Castle Peak (4 108MW)
and Penny's Bay (300MW) power stations, with the total installed capacity
being 6 283MW. Two more 312.5MW generators are scheduled
to be commissioned at the Black Point power station during 2005-06.
   The associated transmission and distribution systems are wholly owned by CLP Power. Its transmission system operates at 400kV, 132kV and 66kV, and distribution is effected mainly at 33kV, 11kV and 380 volts.
   The
CLP Power and HEC transmission systems are interconnected by a cross-harbour
link. This provides emergency back-up and achieves cost savings to consumers
through economic energy transfers between the two systems and a reduction
in the amount of generating capacity that needs to be kept as spinning
reserve against the tripping of other units. The interconnection, commissioned
in 1981, currently has a total capacity of 720 megavolt-amperes
(MVA) (i.e. 720 000 kilovolt-amperes (kVA)).
   CLP Power's system is also interconnected with that of the Guangdong Electric Power Holding Company (formerly named the Guangdong General Power Company) in the Mainland and electricity is exported to Guangdong Province. Such sales are made from existing reserve generating capacity and are governed by an agreement with the Government, signed in March 1992, under which CLP Power's consumers receive priority of supply and 80 per cent of the profit from the sales.
   In
1985, the Hong Kong Nuclear Investment Company (a wholly-owned
subsidiary of the CLP Holdings Limited) and the Guangdong Nuclear Investment
Company (wholly owned by the Chinese Ministry of Nuclear Industry) established
the Guangdong Nuclear Power Joint Venture Company, to build and operate
a nuclear power station at Daya Bay in Guangdong. This comprises two 984MW
pressurised water reactors which went into commercial operation in February
and May 1994, respectively. CLP Power undertook to buy about 70 per cent
of the station's power to meet part of the longer-term demand for electricity
in its supply area.
   Through
its affiliated company, the Hong Kong Pumped Storage Development Company
Limited, CLP Power has the right to use 50 per cent of the 1 200MW
capacity of Phase 1 of the Guangzhou Pumped Storage Power Station, at
Conghua. Off-peak electricity from the CAPCO system and Guangdong Nuclear
Power Station is used to pump water from a lower reservoir to an upper
one. The water is allowed to flow downhill during the day to generate
electricity to meet Hong Kong's peak demand.
   The
Government signed Demand Side Management (DSM) Agreements with the respective
power companies in May 2000 and approved the companies' DSM Resource Plans
the next month. The power companies implemented their three-year
DSM programmes, including rebate schemes for lighting and air-conditioning
systems for non-residential customers, as well as other education and
informational schemes, starting from July 2000. CLP Power and HEC ceased
accepting new applications for joining the lighting rebate schemes in
July and August 2001, respectively, due to exhaustion of the allocated
budgets. The need for extending the rebate scheme to residential customers
is being reviewed by the Government.
   The Electricity Ordinance, with its subsidiary regulations, is the main enabling legislation on electrical safety. It sets out the legal framework encompassing all the areas within which the concerned legislation shall apply, including the registration of electrical workers/contractors and competent persons, the safety standards and requirements for electricity supply, electricity supply lines, electrical wiring and products.
   Since
1990, the regulations concerning registration of electrical workers and
contractors, the safety of electrical wiring, and the supply of safe household
electrical products have come into effect in stages. At December, some
8 000 electrical contractors and 51 500 electrical
workers held valid registration.
   A new regulation, namely the Electricity Supply Lines (Protection) Regulation (ESLPR), commenced full operation from April 1 to protect electricity supply lines from damage during works activities, in the interests of safety and of ensuring the continuity of electricity supply. A Code of Practice on Working Near Electricity Supply Lines was published in June 2000 to provide general guidance on how to satisfy the requirements of the ESLPR. Some 570 competent persons have been approved under the ESLPR for locating underground electricity cables since June 2000.
   In
2001, in enforcing the Electricity Ordinance, the Government conducted
13 442 site inspections to check the safety standards of
electrical installations and electrical product supply outlets, and 390
prosecutions were instituted against violations.
|